Time frame: 02.03.2026 - 30.05.2026
Location: Jasper
General Contractor: BuildIT
Man power: 2- 10 workers
Type of millwork: HighEnd Hospitality Millwork
Challenges: The Project was a high-pressure installation with a large amount of work to complete before the scheduled opening.Items installed - is the face of the hospitality, first thing guests see, every detail had to meet a high visual standard, leaving no room for errors or rework.
The project required strong coordination with other trades, flexibility around changing site conditions, and careful planning around millwork deliveries. In the final stage, the schedule became extremely tight, and the team worked shifts of up to 21 hours to complete the installation on time while maintaining the required level of quality and precision.
We have completed on site machining for 25+ doors, including electrical locks, mortis locks, deadbolts, flush bolts. Manufactured the templates on site to increase the speed of the process.
Copyright © 2025 Karbonit - All Rights Reserved.